Illustration of the connection process.
Latest update: October 23, 2026 — following the October 22 meeting

Construction continues in White Rock
Crews are continuing work on the Atomic Fiber network in White Rock. As construction progresses, a separate connection crew is preparing to begin work on individual home connections in selected areas. This is the next step toward bringing fiber into homes and getting customers ready for activation.
Timing shared at the October 22 meeting
Bonfire said first activations were possible in December 2026, with January 2027 more likely. These were estimates, not confirmed appointments for individual homes. Los Alamos Phase 1 crews were expected later in 2026 or early 2027; the meeting did not confirm a December or January activation date specifically for Los Alamos.
We will coordinate the next steps with you
Customers in areas moving toward home connections will be contacted to arrange a visit and review the work needed at their property. Atomic Fiber described a scheduled property survey to discuss the point of connection, indoor ONT location, proposed route and any irrigation, landscaping, driveway or access concerns. Bonfire described before-and-after photographs and restoration as close as possible to the prior condition.
LANet can help arrange these meetings and keep you informed about what the installation involves, what happens next and when work is expected for your address. Outside connection work and the final service activation may take place at separate appointments. We will confirm the arrangements with you as your home becomes ready.
What happens on installation day?
When your fiber connection is ready and your installation appointment is confirmed, LANet will come to set up your router, check the fiber connection and test your service. We will make sure your devices can connect and that your internet is working before completing the visit.
We will continue sharing progress updates and contacting customers about their individual installation steps. Construction activity nearby does not by itself confirm that an address is ready for activation, and timing can vary by location.
Get ready for your connection
Questions or help coordinating a visit? Call or text (505) 412-6282 or email info@losalamosnetwork.com. If you have already submitted the fiber interest form, you remain on our list. Keep your existing internet service until your new fiber service is confirmed working.
Earlier report: September 21, 2026
The report below records the planning estimates and installation information shared in September. The dates, preparation windows, conduit depth and visit durations below are historical planning information, not current guarantees or universal installation instructions. The October 22 meeting guidance above takes precedence; route and equipment decisions require an individual survey. LANet will provide address-specific updates as work progresses.
Phase 1 White Rock Fiber Construction Update
Construction is moving forward on Phase 1 of the Atomic Fiber network in White Rock. LANet recently met with the Bonfire team to review construction progress, the current projected schedule, and what customers can expect as their homes get closer to activation.
Schedule estimated in September 2026
Based on the latest information provided by Bonfire:
- The first service area includes approximately 149 White Rock addresses.
- This first area is currently projected to be ready around mid-December.
- A second area is expected shortly after the beginning of January.
- A third area is projected for the middle to latter part of January.
These dates are estimates. Construction progress, network testing, weather, utility conflicts, and completion of the main network connection could affect the schedule.
LANet will continue meeting with Bonfire and publishing updated information as it becomes available.
What happens before your fiber is activated?
Bonfire plans to begin preparing individual properties approximately 15 to 45 days before each neighborhood fiber distribution area becomes serviceable.
Customers may notice several steps taking place:
- Utility locating: New Mexico 811 will identify existing utilities. Paint or small flags may temporarily appear near the property.
- Fiber conduit installation: A contractor will install a small underground conduit from the neighborhood fiber connection to the utility side of the home. This conduit will generally be installed approximately six inches underground.
- Fiber drop preparation: Bonfire will photograph the area before and after completing the work. In most cases, the customer will not need to be home for this part of the process.
- Final activation: Once the neighborhood network and the individual fiber connection are ready, LANet will contact the customer to schedule an activation appointment.
Where will the fiber enter the home?
The exterior fiber connection will normally be installed on the same side of the house where the other utilities enter.
During the final appointment, the installation team can route ruggedized fiber around or under the house when another entry location is preferred.
Customers should let LANet know in advance about:
- Private sprinkler or irrigation lines
- Locked gates
- Landscaping concerns
- Pets in the yard
- A preferred route or entry point
- Any other special property conditions
If a customized underground route is requested, an additional site survey may be necessary.
What happens during the activation appointment?
The final activation appointment is expected to take approximately one to two hours, and an adult will need to be home.
During this appointment, the technicians will:
- Complete and activate the fiber connection
- Bring the service into the home
- Install the LANet-managed router
- Test the connection
- Confirm that the customer is online
LANet and Bonfire are coordinating the process so the fiber connection and LANet equipment can be completed as efficiently as possible.
Should I cancel my current internet service?
Please do not cancel your existing internet service until LANet has confirmed your activation appointment and your new fiber connection is working.
Existing LANet wireless customers will continue receiving their current service while waiting for fiber to reach their address. LANet will contact customers individually when it is time to transition.
Have you already submitted your information?
LANet is tracking current customers and new households that have expressed interest in Atomic Fiber. If you have already completed our fiber interest form, you remain on our list.
Submitting an interest form does not mean your installation has been scheduled. We will contact you when construction reaches your area and we have more specific information for your address.